[Build] jim can spray monday....
jim
jim at well.com
Sun Sep 13 22:14:02 UTC 2009
best to finish the prep properly. main things
are to prep surfaces so that paint will stick (no
loose paint, no grease or wax) and also to mask
things, including all the things no one will
notice until we start up the spray gun (e.g. the
top of the electrical storage room, the toilet,
door knobs...).
once the spray gun starts up, it'll be a lot
of time to stop it for more than a short time,
so let's get the prep and masking done right so
we can start up and go till we're finished.
note that if there are spots that are not
sprayed for whatever reason, we can come back
and fix whatever's the problem and brush paint
to cover.
i'm sure after the first coat we'll discover
cracks, holes, and other problems that will
need attention before we put on the second (and
final) coat.
i plan to show up monday around noon. if the
prep isn't done yet, no problem, i'll help out
and expect we can start spraying tuesday.
again: much better to complete the prep and
masking rather than start spraying and then
have to stop (and clean the gun and re-"box"
paint, etc.
On Sun, 2009-09-13 at 13:28 -0700, miloh wrote:
>
>
> On Sun, Sep 13, 2009 at 12:45 PM, Rubin Abdi <rubin at starset.net>
> wrote:
> jim wrote, On 2009/09/12 22:47:
> > as a reminder, i was once a good paint
> > sprayer. i can spray the place out. i can
> > start monday, if things are ready (prep
> > done, stuff masked, paint on location,
> > requisite accessories (e.g. extra buckets,
> > strainers...) and probably get the first
> > coat on by the end of the day.
>
>
> We prepped about 90% of the walls last night. The only thing
> left was 2
> columns that had stuff sitting around them and the back
> windows/dj
> booth. The area around the kitchen (and darkroom) has been
> left
> untouched as there's still pipe work happening there.
>
> Just a note, as of last night there was no paint that I could
> find in
> the space.
>
>
>
> There are unused conduits hanging off the ceiling
> The east wall needs prep work
> The bare sheetrock needs primer
> Plastic sheeting needs to be taped out...
>
> The paint prep job is only 50% done as is, needs another day of
> work....
>
>
>
>
> --
> Rubin Abdi
> rubin at starset.net
>
> _______________________________________________
> Build mailing list
> Build at lists.noisebridge.net
> https://www.noisebridge.net/mailman/listinfo/build
>
>
More information about the Build
mailing list