i got questions, including "does anybody have any
opinions or ambitions i should look out for" as well as
"is anybody interested in helping with these?"
what's supposed to be happening in the Scott Memorial
Construction Room (SMCR) east of the darkroom?
I like the idea of moving the construction materials
from the walking way around the cook area into the SMCR.
Anybody up on the state of the possibility of moving
the "dirty workshop" aka "matfablab" aka "fabmatlab" to
the east end (where the Church classroom is now)?
Anybody up on the state of redoing lights and tracks
over the fabmatlab and turing and church classrooms?
I'm kind of preparing myself to do more electrical
work, likely end of this coming week (july 8,9 or so).
Immediate projects include
* run some outlets around the turing and possibly even
the church classroom walls.
* run conduit for light switches in the turing and
possibly church classrooms.
* help bring down the light fixtures and power rails
over the fabmatlab, the turing and church classrooms,
and probably the walking way near the big pile of
construction materials.
* bring power to the ceiling for the re-hung lights and
power rails.
* rampage in the little storage closet: build another
set of shelves (plywood is cut, needs 2x4s cut to size)
above the exist shelf stack as well as maybe put up
shelves and cable hanging stuff above and near the door.
More information about the Build