On Thu, Jul 16, 2009 at 4:50 PM, jim<jim at well.com> wrote:
>> Hm. One thing to consider of course is that we needn't do the entire
>> space. Rough work rooms, for example, probably don't need the
>> prettification.
> JS: sealing them tends to get rid of the risk of grodiness
> (worst case: blood poisoning from a splinter or fall) and
> also makes it much easier to clean things up (e.g. metal
> filings, spills).
What about laying down rubber work mats? (I've no idea about cost, but
at least it's dead simple.)
> Seems to me easiest to demo the place and then do the
> floors when stuff is mostly out of the way rather than
> do floors after walls and partitions and such are up
> and in the way of a long straight sanding run.
Which in turn means flooring is high priority so that other buildout
can be done.
- Sai