[Build] Upcoming dirty shop work for Reboot, and a need for Volunteers.

Torrie Fischer tdfischer at hackerbots.net
Thu Jul 17 05:03:42 UTC 2014


That is the plan, yes. We need to acquire sheets and such like that, which I 
held off on bringing together since I'd rather figure out what makes a good 
plan for you. I'll call you tomorrow and see what we can figure out :)

On Wednesday, July 16, 2014 20:46:48 neil maclean wrote:
> Hi Torrie,
> 
> I'm no expert. I did sand the floors in my own flat. I was amazed at the
> unbelievable amount of dust the sander created. After it was over,
> everything needed a major cleaning. Before it started, I removed as many
> things as possible from the rooms.
> 
> If you plan to sand NB in sections consider buying plastic sheets and
> taping off areas floor to ceiling where you'll be sanding to try to keep
> the dust in those areas.
> 
> We can work together so we trade off work in different areas.
> 
> Give me a call or lets try to meet so we can coordinate.
> 
> Neil
> 415 515-8430
> 
> On 7/16/2014 6:03 PM, Torrie Fischer wrote:
> > Hiya, Neil!
> > 
> > I was planning on starting on sanding the floor Thursday evening to
> > refinish it, but if that would cause issues or introduce unnecessary
> > constraints please let me know. Its not a big deal to delay it 'till this
> > weekend.
> > 
> > On Wednesday, July 16, 2014 17:59:22 jarrod hicks wrote:
> >> No worries, sanding the shop can wait.
> >> 
> >> There are plans to sand the floors of part of the main space starting on
> >> Thursday evening, will this work as long as your tools are covered and
> >> away
> >> from the sanding zone?
> >> 
> >> Torrie sent an email to the build list to check if starting on Thursday
> >> at
> >> 1800 was okay with everyone. I don't know if you are subscribed to that
> >> mailing list. I am copying Torrie on this message.
> >> 
> >> On Wed, Jul 16, 2014 at 5:13 PM, neil maclean <neil at warmcove.org> wrote:
> >>>   Hi Jerrod,
> >>> 
> >>> I got most of the pipe installed in the shop today. I will get the rest
> >>> tomorow along with pulling the wire and putting on the covers. I'd ask
> >>> you
> >>> to refrain from sanding until after as the dust tends to get into
> >>> everything. If you really want to sand, please take my tools etc out of
> >>> the
> >>> space.
> >>> 
> >>> thanks so much.
> >>> Neil
> >>> 
> >>> On 7/6/2014 11:31 PM, jarrod hicks wrote:
> >>>   This schedule is rough and specific times on these have not been
> >>> 
> >>> determined. I will provide access as best I can for volunteers who can
> >>> come
> >>> in to help with these tasks. Please let me know if you can help and
> >>> when.
> >>> 
> >>>   W-09: Evening: Move things away from walls. Consolidate/purge
> >>> 
> >>> tools. Make an inventory and shopping list for materials
> >>> 
> >>>   R-10: Re-Frame Doors. Finish Drywall at openings. Patch as needed.
> >>> 
> >>> Remove Hazards
> >>> 
> >>>   F-11: Mud and Tape drywall. Bonus: Purge remaining. Remove Hazards
> >>>   
> >>>   
> >>>   S-12: Drywall second coat. Bonus: Tool repair/maintenance. Remove
> >>>   Hazards
> >>>   
> >>>   
> >>>   U-13: Sand and Paint walls, 2 coats. Sand and Paint doors. Bonus:
> >>>   Clear
> >>> 
> >>> Shop (Arrange temp. workshop area)
> >>> 
> >>>   M-14: Clear out Shop. Clean/Strip floors.
> >>>   
> >>>   
> >>>   T-15: (Pending electrical and flooring) Install/fix tables and
> >>>   Shelving.
> >>> 
> >>> Replace tools. Install peg boards. Fix tool chests.
> >>> 
> >>>   W-16: Label/Organize shelving. Setup project and art shelves.
> >>>   
> >>>   
> >>>   R-17: Create and install safety signage. Bonus: Tool
> >>>   repair/maintenance.
> >>>   Remove>
> >>> 
> >>> Hazards
> >>> 
> >>>   F-18: Create and install safety signage. Bonus: Tool
> >>>   repair/maintenance.
> >>>   Remove>
> >>> 
> >>> Hazards
> >>> 
> >>>   S-19: Time overrun allowance. Complete unfinished tasks. Remove
> >>>   Hazards
> >>>   
> >>>   
> >>>   U-20: Time overrun allowance. Complete unfinished tasks.
> >>>   
> >>>   
> >>>   July 19-Aug 1 Set up active ventilation. Purchase new
> >>>   tools/consumables.
> >>>   Build>
> >>> 
> >>> scrap bin.
> >>> 
> >>>   Considering that I have never done drywall work and will be learning
> >>>   as
> >>> 
> >>> I go, anyone who can teach these skills would be really appreciated. It
> >>> would be a cool bonus if a short drywall installing, mudding, and taping
> >>> class could be held for others who are interested. Even so, anyone
> >>> willing
> >>> to learn/figure out how to do this with me is welcome.
> >>> 
> >>>   I will be collecting whatever tools and materials we have for drywall
> >>> 
> >>> work, and purchasing others. So if you need to do drywall/carpentry work
> >>> outside the shop they should be available in the space. If you have
> >>> tools
> >>> that can be lendt, please let me know as well, as well as any
> >>> recommendations for purchases/materials.
> >>> 
> >>>   Cheers.
> >>> 
> >>> -Jarrod
> >>> 
> >>> 
> >>> _______________________________________________
> >>> Build mailing
> >>> listBuild at lists.noisebridge.nethttps://www.noisebridge.net/mailman/listi
> >>> n
> >>> fo/build
-------------- next part --------------
A non-text attachment was scrubbed...
Name: signature.asc
Type: application/pgp-signature
Size: 198 bytes
Desc: This is a digitally signed message part.
URL: <http://lists.noisebridge.net/pipermail/build/attachments/20140716/71def846/attachment-0003.sig>


More information about the Build mailing list