>    verify overhead tracks is a matter mainly of opening the junction
> box that feeds the track to verify that it's feeding 120 VAC, then
> determining which rails inside the track are hot, return, and ground,
> then verifying that a gizmo plugged in presents the right voltages to
> the right pins in the receptacle.

one thing that scott (bath contractor guy) mentioned was that each of
the gizmos should probably be checked. some were definitely jankier than
others (at least in terms of strain relief and wiring).

\p

---
A specification, design, procedure, or test plan that will not fit on
one page of 8.5-by-11 inch paper cannot be understood. - Mark Ardis