[Build] Flooring update

Torrie Fischer tdfischer at hackerbots.net
Fri Jul 18 15:48:19 UTC 2014


On Friday, July 18, 2014 07:11:12 neil maclean wrote:
> Hi torrie, and build@
> 
> Thanks for moving things along.
> Here's a link to the type of floor coating I was suggesting:
> http://www.rustins.eu/Details.asp?ProductID=901
> It drys quicker, is water based so easier to clean (possible to actually
> clean up tools without using alcohol based solvents,) and the finish is
> just as hard I think. There are lots of manufacturers, so I'm not
> suggesting this exact maker.
> Here's the other type: http://www.rustins.eu/Details.asp?ProductID=784

Excellent, thanks a lot!

> 
> Really glad we got it down to three sections and you helped us write
> down/finish the electrical plans with the new-improved layout.

Pretty sure I just decided to walk away and move chairs instead of getting 
sucked into the electrical discussion, so I think Matt deserves the credit for 
that :)

Still, yeah, ~progress~!

> 
> Neil
> 
> On 7/17/2014 8:55 PM, Torrie Fischer wrote:
> > Hi, build@
> > 
> > Neil the electrician came in today and we discussed a better plan of
> > attack
> > that would work well with his plans.
> > 
> > He doesn't want to get in the way of the flooring work and we don't really
> > want to hamper his electrical efforts, so we're going to handle the space
> > in three big chunks.
> > 
> > For reference, the original plan I submitted:
> > 
> > http://i.imgur.com/BzUZVtJ.png
> > 
> > We're going to try and cover the big area labeled #1, while Neil works on
> > doing electrical work on the rest of the space. Should take most of
> > saturday to get our sanding/cleaning work out of the way on Saturday with
> > application of the floor sealant on Saturday night or Sunday.
> > 
> > Once that is done, we'll move things out of areas #3, 8, and 9 (the rooms)
> > into the big area for storage and Neil will work on the electrical in the
> > rest of the space.
> > 
> > Following that, we'll repeat the pattern with the rest of the space.
> > 
> > We've acquired enough tools and plastic sheeting to make this possible
> > thanks to the generous monetary contributions of Michael Schaffer <3
> > 
> > Floor coatings still need to be acquired and will be planned out on
> > Friday.
> > 
> > However, prior to doing any sanding, we need to patch more holes in the
> > now- accessible walls and do some painting of conduit and walls. Ask
> > piratematt about that, but more details should be available soonish. :)
> > 
> > One way or another things will be happening on Saturday be it painting,
> > sanding, patching drywall or sealing the floor!
> > 
> > 
> > _______________________________________________
> > Build mailing list
> > Build at lists.noisebridge.net
> > https://www.noisebridge.net/mailman/listinfo/build
-------------- next part --------------
A non-text attachment was scrubbed...
Name: signature.asc
Type: application/pgp-signature
Size: 198 bytes
Desc: This is a digitally signed message part.
URL: <http://lists.noisebridge.net/pipermail/build/attachments/20140718/a0457adf/attachment-0003.sig>


More information about the Build mailing list